Site Prep for a New Build or Slab: Clearing to Compacted Pad

Golden Isles Fencing and Excavation 2026-11-20

What happens to your building over the next 50 years will be dictated by what lies beneath. The part you never take pictures of. The part that will determine if your slab is cracked.

The process and reason for the process is below.

The order of operations

1. Survey and layout

First we locate the building on the site (property corners, setbacks, easements and the building footprint is staked). We establish elevations from a fixed benchmark (in the flat coastal landscape the relative level of the finished floor to the surrounding grade can be one of the most important decisions you will make).

For anyone located in or even near tidal marsh, creek or wet land, here's where you verify wetlands and buffers. Not later. See clearing near marsh and wetlands.

2. Erosion and sediment control

You install silt fence and other controls BEFORE you disturb. It's a requirement (not a courtesy) on most of the jobs you have a permit for. It gets inspected. Plus it ensures that your topsoil isn't going down the street with the first storm.

3. Clearing and grubbing

Two separate things. And it's a huge difference.

Clearing is the removal of that which is above: trees, bush, undergrowth.

Grubbing is the removal of that which is below: stumps, root balls, underground organic matter.

When preparing a site for a building pad, grubbing is not optional. If you don't remove organic matter from beneath the ground it will decay and compress and cause void spaces. Then your structure above will settle into the void spaces unevenly. And that differential settlement leads to cracked slabs and racked door frames. This is by far the most common major shortcut in site prep.

We also strip topsoil from the pad area, as topsoil is organic and can compress. It's best to stockpile on site for later landscaping purposes instead of hauling it away to buy it back.

More on this phase and the cost for it: land clearing cost per acre.

4. Cut and fill

Site is contoured to design elevations (ie fill in low spots, cut in high spots). On the flat (a lot of lots in Brunswick are flat) lots, often there's not much to cut and that means you need to bring in fill.

A lot of budget goes here. You need to be careful about what you are getting in for the material.

5. Structural fill, placed in lifts

Fill under a building is not the same as fill in a garden bed. It needs to be structural fill. No organic matter and trash in it. Clean granular material that will compact the way it's supposed to.

You've got to lay it in lifts (thin layers, usually six to eight inches). You compact each layer before you add the next. It's not enough to dump three feet of soil and then just roll a machine over the top. That top four inches will get compacted, and then you're leaving the rest of it to settle out over the next ten years.

Also, you've got to watch moisture content. You really only want the soil to be in a specific moisture range in order to compact it the way it's supposed to. If it's too dry, it's not going to knit. If it's too wet, it will pump instead of densifying. Out here, too wet is the common issue, and there's a legitimate reason why work shuts down when it rains a lot.

6. Compaction testing

It depends. With engineered projects they check with the testing lab to make sure you are getting a certain % of max density. On smaller residential projects it is more a "feel" or "I've seen it so many times I know it's good" thing.

For your project if you have an engineer's specs then this is how you know that the engineer's specs were met. It's not a bad amount of money. It's the only way to know objectively what's going on under the building you are building.

7. The pad, shaped and drained

The resulting pad is elevated above the surrounding grade and contoured to shed water rather than accumulate it. On low coastal lots, this is of critical importance since the elevation of the pad is often what protects the structure from standing water during a wet season.

You design the drainage now around the pad rather than retrofitting it. That rough rule of about six inches of fall in the first 10' away from the structure is established at this point. Adding drainage retroactively around a completed structure is much more costly and never as effective (see standing water on flat coastal lots).

8. Utilities and final trimming

Dig for water, sewer or septic, power and comm lines, usually before the slab so that nothing needs cutting afterwards. Trim pad to final grade. Install any vapour barriers & sub-base, turn over to slab contractor.

Open utility trench with pipe laid in the bottom and a mini excavator parked at the head of the run
Trenching a service line across a wooded lot, spoil banked to one side so it can go straight back in.

What makes coastal site prep different

A high water table. Ground water close to the surface is a big issue on low lots: affects how deep you can dig, if the trenches will stay open, if you can compact the fill, and how high your pad should be. Sometimes dewatering is necessary.

Sandy soils. They'll compact pretty well. They won't hold a cut face. You have to pay attention to the trench walls. It's not just a box to check for erosion control.

Clay layers. Typically a foot or two down. Clay retains water above it, that's why that 'sandy' looking lot might be a bathtub. Also bad as fill.

Flood zones. A lot of this is mapped. If it's mapped, it's got a minimum required finished floor elevation. That sets your pad height, which sets your fill volume, which sets a lot of your cost. Check with Glynn County Community Development early for your flood zone and any elevation requirement. It can make a big difference in your project budget.

Rain. Our summer storms stop earthwork. You need to be flexible in your schedule, especially June through November.

What it costs, roughly

Site prep is a per job cost, with a large variance. Easy pad on clear relatively level suburban lot may be in the $5,000 to $15,000 range. A lot that needs major clearing. A lot that requires heavy import to meet flood elevation. Long utility run. Well above that.

Major drivers:

  • Imported fill volume. Usually the biggest single cost. They charge by the load. There can be a lot of loads if you happen to be on a low lot and need to come up to a flood elevation.
  • Clearing and grubbing extent, and what to do with the debris.
  • Access for equipment and trucks.
  • Spoil removal if not possible to have the excavated material on site. See hauling.
  • Testing and permits.

Questions worth asking your contractor

  1. Is it inclusive of grubbing and topsoil stripping? Where is this going?
  2. What fill are we calling for? Where is this coming from?
  3. What's the thickness of the lift? How do you prove you're compacting?
  4. What is pad elevation? How'd you come up with that?
  5. Are we looking at erosion control? Who is going to maintain it?
  6. What do we do if we run into groundwater?
  7. What are we not looking at? Utility connects and permits is a big one.

An experienced contractor can answer the above with little trouble.

White vinyl privacy fence and gate wrapping a new concrete slab at dusk
Fence in before the rest of the build, so the site is secure while the work carries on.

We do this work

We do new construction & slab clearing, grubbing, grading, fill, compaction, excavation in Glynn, Camden, McIntosh & surrounding areas. And we will be straightforward if you need more fill than you thought on your lot.

Ask for a free site visit or call (912) 674-0619.